Scroll

CyrusOne (Building 1 – Phase I and II)

CyrusOne (Building 1 – Phase I and II)

San Antonio, Texas

Architect: Corgan Associates

Owner: CyrusOne

This two-phase, 200,000-SF project was completed in nine months and included the following equipment:

  • 8 – 2.25-MW generators
  • 24 – 750-kW UPSs
  • 48 – 600A STS/PDUs
  • 8 – 474-ton chillers
  • 24 – 6,000 CFM CRAC units

Phase I included an 86,297-SF build-out of Data Hall, including 40,000 SF of white space. 2.25 MW Day 1 with infrastructure included allowing an immediate expansion to 4.5 MW. The 29,733-SF interior finish-out includes the office, main lobby and corridors of the existing shell building.

Phase II encompassed the complete MEP fit-out of the existing facility as well as a tenant office fit-out. During Phase I, Rogers-O’Brien installed 2.25 MW, and in this second phase included 6.75 MW for a total of a 9-MW facility. This second-phase schedule was 16 weeks from start through level 5 commissioning. 



2.25 MW Critical Power in Phase 1 200,000 Total SF 6.75 MW Critical Power in Phase 2

Project Details

  • PROJECT DURATION: PHASE 1: 14 WEEKS, PHASE 2: 16 WEEKS
Space to Network