RO completed Phase 1 of DataBank’s Plano campus expansion with the delivery of a 126,000-square-foot, three-story addition to the existing DFW3 facility. The Tier III data center was designed to provide up to 40MW of critical IT power and constructed to integrate seamlessly within an active campus environment, adding significant capacity while supporting DataBank’s cloud platforms, secure storage, and disaster recovery services. Building on this successful delivery,

RO has been awarded Phase 2 of the project and is currently under construction on a 26MW, two-story fit-out of the existing data center space at DataBank’s DFW8 campus, continuing our long-standing partnership delivering mission-critical infrastructure.



Owner: DataBank Data Centers

Project Highlights

  • Repeat Client
  • Tier III Data Center
  • 40 MW Phase I
  • 26 MW Phase II