Rogers-O’Brien provided construction management services to FedEx Ground for the site development that included approximately 100 acres with construction of a 330,000 SF package distribution center and ancillary buildings. The project duration was 360 calendar days, start to finish schedule.  105 days into the project the first area was completed and turned over to the owner’s conveyor contractor for installation to begin. The building was divided into seven areas with 12 milestones associated to them. Rogers-O’Brien Construction coordinated with the conveyor and equipment installers and met or exceeded all milestone dates. This coordination resulted for a successful project for all team members.