CyrusOne SAT II Westover Hills

San Antonio, Texas

In Progress
image description
  • Phase 1: 86,297 SF build-out of Data Hall including 40,000 SF of white space.  2.25 MW Day 1 with infrastructure included allowing immediate expansion to 4.5 MW.   29,733 SF interior finish out of office, main lobby, and corridors of existing shell building.
  • Phase 2: Phase 2 consists of a 34,800 SF build-out of Data Hall 2 and Office/Lobby finishout.  Also included in the scope is the complete MEP fit-out of the existing facility.  During phase 1 RO installed 2.25MW and the 2nd phase includes an installation of 6.75MW for a total 9MW facility.  The phase 2 portion schedule is 16 weeks from start through level 5 Commissioning.
  • Cyrus 1 SAT Building 2: 189,000 SF Ground up 2-story tilt-wall data center.  Scope also includes retaining walls, site work for an additional facility and the finishout of the 2-story data hall.